NEWSLETTER

 
Enter your email:

Construction Topics

GENERAL TECHNICAL KNOWLEDGE

SITE WORK

CONCRETE

MASONRY

METAL

CARPENTRY & WOOD

THERMAL & MOISTURE

DOORS & WINDOWS

FINISHES

SPECIALTIES

EQUIPMENT

FURNISHINGS

SPECIAL CONSTRUCTION

CONVEYING SYSTEMS

MECHANICAL

ELECTRICAL

PEOPLE SKILLS

JOBSITE MANAGEMENT

ADS

Become a FB fan


Construction Network


Trades Hub

 

CONSTRUCTION KNOWLEDGE  >> CONCRETE >>

SLABS ON GRADE
 


 

1. What are the Basics of Slabs on Grade?
2. How do the Joints Work for Slabs on Grade?
3. What Should I Know About Installing Slabs on Grade?
4. What Public Domain Documents are Available for Further Study?
5. Tricks of the Trade & Rules of Thumb for Slabs on Grade:


What are the Basics of Slabs on Grade?


People outside the construction business wonder what can be complicated about a “cement” floor. If they only knew. The concrete floor is often the most used, and noticed, part of the building. With that amount of importance, one would think that we would usually get them right. Unfortunately, it is all too rare that the concrete floor meets the criteria of Owner, design professional and contactor through out the life of the building.
 
You may wonder, “Why is it so difficult to obtain and economical, serviceable concrete floor.” The best way to approach this question is to examine some of the things that go wrong. Generally problems stem from construction practices, materials, or improper design. A list of concrete floor problems follows:

  1. Cracking – structural
  2. Cracking – shrinkage
  3. Curling- Top of slab shrinks more than bottom and slab edge lifts.
  4. Scaling – Hardened concrete breaking away from slab top in sheets 1/8” to ¼” thick.
  5. Dusting – Appearance of powdery material at slab surface.
  6. Crazing – Many fine hairline cracks in a new slab which resemble a road map.
  7. Spalling – disintegration of concrete at joint edges.

In order to avoid the above problems, all the details of a concrete slab, from design to curing, must be performed appropriately. Due to the importance of the floor, we will examine a step-by-step procedure for obtaining an acceptable concrete slab-on-grade.
 
The first step in the process is the concrete design mix. Rarely does low quality concrete produce a high quality floor. A 4000 psi concrete is recommended instead of a 3000 psi mix due to the higher cement content and improved wear resistance. The Portland Cement Association recommends that a commercial or industrial concrete floor use a concrete with a three day compressive strength of 1800 psi. This requirement provides early protection from construction traffic. Water-cement ratio is also critical for concrete slabs-on-grade in order to minimized shrinkage cracking.


How do the Joints Work for Slabs on Grade?


The proper design and location of joints is an area of confusion throughout the construction industry. There are three types of joints:

  1. Isolation Joint – Used to prevent a bond and allow movement between the slab and the adjoining structure.
  2. Control Joint – Used to induce shrinkage cracking at specific locations.
  3. Construction Joint – Used to provide a stopping place for a concrete pour. The construction joint can also be detailed to function as an isolation or control joint.

The basic theory of joints must be understood in order to use the correct joint at the correct location. The isolation joint should be used to allow the concrete floor and the rest of the structure to act independently. There is not key way or bond of any type through an isolation joint, allowing movement both horizontally and vertically. The figure below illustrates a typical isolation joint detail and a plan of an isolation joint at a steel column. The isolation joint at a column is often in the diamond shape so the slab control joints stop on an isolation joint corner (this reduces cracking). The isolation joint diamonds must also be formed separately and poured after the floor slab.
 
The joint sealing compound shown is another topic worthy of discussion. The installation of joint sealers is costly because the expansion joint material must be kept about ½” low and a removable strip installed. The sealant installer can remove this strip and begin sealing. I have seen many cases where joint sealant was shown on drawings, with perhaps a less than full awareness of cost by the design professional, and then never installed in the field.
 
This is a bad situation for everyone, since the owner paid for something he didn’t get and the contractor left himself open for claims. When joint sealant is shown on the drawings, I think it advisable to discuss costs, requirements and details with the owner and design professional to agree on what should be performed in the field.

The control joint functions as a contraction joint, allowing the shrinkage of the concrete slab to occur in one location rather than random cracking in the slab. A control joint is a weakened plane in the slab that is supposed to rack. If a crack appears two feet (and parallel) from a control joint, one can be reasonably sure the control joint did not create a weakened plane. Isolation joints always function as control joints and construction joints usually do.
 
Three types of pure control joints are shown in figure below. The saw cut joints are sawed by a concrete saw as soon as the saw does not crack the saw cut edges. If one waits a few hours too long to saw cut, the slab shrinkage may have created its own cracks. A saw cut is typically considered adequate to a depth of ¼ the slab thickness. The induced crack that form below the saw cut is usually jagged enough to continue lock the slabs together and prevent differential settlement. It is also possible, though not common, to use smooth dowels through a control joint that are coated to prevent bond.
 
For thicker slabs, a crack inducer can be placed on the sub-grade to reduce the thickness of the saw cut required. Finally an insert can be placed in the plastic concrete to create a control joint. The insert can be a simple hardboard strip or one of several products on the market for this use. Care must be taken to keep these pre-molded insert strips straight while installing.


 
A construction joint is first and foremost a place to start and stop pouring concrete. The details of a construction joint can allow it to act as a isolation joint, control joint, or continuous joint. The butt joint acts as an isolation joint allowing both vertical and horizontal movement. The dowel control and keyed joints both act as control joints, allowing horizontal movement but preventing vertical movement. Finally the doweled continuous joint should allow no movement.
 
While the construction supervisor should never just change the concrete slab joint details to something that seems to make more sense, he should consider the joints required and make appropriate recommendations to the owner or design/professional. Concrete floors are too much work to do a second time.


What Should I Know About Installing Slabs on Grade?


The many specific details of forming, placing, finishing, and curing a concrete slab are not included here. The information presented here highlights trouble areas that a construction supervisor can concentrate on to try to achieve an acceptable concrete floor. In order to review all the specifics of concrete floor construction, however, I would recommend a publication from the American Concrete Institute entitled “Concrete Craftsman Series – Slabs-On-Grade”.
 
An area of the floor system that is crucially important is the sub-grade on sub-base. The most important item is proper compaction; many floors settle and have structural cracks. Of course organic material can not be properly compacted and must never be in the sub-grade. It is a simple fact that the floor system rests on the grade and if the sub-grade settles the floor settles.

Particular attention should be paid to backfilling trench and footing excavations under a floor. While it is worthwhile to make the contractor perfuming the work responsible for the quality of backfill, the construction supervisor should realize that his step, by itself, may not solve the problem. The contractor backfilling under a future slab must clearly understand the required quality level of the backfill and assure its acceptability.
 
Forming of concrete floors is reasonably straight forward. One must remember, though, that loose or warped edge forms cause uneven floors. Therefore, the care taken with the edge form setting will be proportional to final flatness of the floor.
 
Placing concrete in hot weather, particularly when the walls and roof are not yet completed, creates some additional quality concerns. Plastic cracking is one of the worse problems that occur. Plastic shrinkage cracks form before the concrete hardens and are caused by hot, dry, and/or windy conditions. The cracks resemble the shrinkage cracks seen in clay soils during very dry weather.
 
Curing can also create lots of problems for concrete floors. Since water evaporates so quickly from the large exposed surface, without proper curing methods a floor is likely to rack, craze and dust. The three most common means of curing are:

  1. Wet cure by covering, after finishing, with continuously watered burlap.
  2. Wet cure by watering finished slab and covering with plastic or paper.
  3. Seal cure with liquid membrane curling compound.

The construction supervisor should verify that the method chosen is acceptable to the Owner and Design Professional.



What Public Domain Documents are Available for Further Study?


The US Dept of Defense produced a 59 page training document that has some good joint details and design guides for understanding Concrete Floors. Titled Concrete Floor Slabs on Grade Subjected to Heavy Loads, the official name is UFC 3-320-06A, 1 March 2005.

This US Department of Army Concrete and Masonry  Field Manual does a great job explaining Concrete and Masonry basics. It's 323 pages of figures, basic explanations and instructions of how to do the work. If you are somewhat new to construction, take some time and review this excellent resource. The official name is US Army FM 5-428.

Another great all around great construction introductory guide that covers some concrete installation items is the US Navy Builder Training Course Volume #1. The official name of this 332 page resource is Builder 3 and 2, Volume #1, NAVEDTRA 14043.


Tricks of the Trade & Rules of Thumb for Concrete Slabs on Grade:


  1. Plan for each isolation, control and construction joint, know and communicate the locations and details.
  2. If the concrete floor finish is critical and construction traffic needs to be on it a few days after placement, get extra concrete cylinders made to break at 3 days to assure 1800 psi strength prior to using the floor.
  3. A smooth sub-grade, without ruts, yields a much better floor, since the concrete can shrink and crack evenly instead of being localized at a rut. Make sure the sub-base placement and the concrete placement don’t make ruts in the sub-grade.