1. What are the Basics of Concrete Footings?
2. How do I Stage and Plan the Job for Footings?
3. How do I Place Concrete Footings?
4. Tricks of the Trade and Rules of Thumb for Concrete
Footings:
Concrete footings exist to transfer the structural loads from the building (snow load, live load, dead load, wind load, earthquake load, etc.) to the Earth. Obviously, the foundations on a building are critical from a structural standpoint. However, since they are usually unseen after backfilling, too many times the foundations are not built without enough attention to detail.
It’s often said that any building project that doesn’t come out of the ground well will be difficult to ever get back on track. It’s important for the Construction Supervisor to understand both the function and the acceptable tolerances on foundations. In order to understand the function, some terms need defined:
While some site work needs to proceed the footing installation, the
planning for the footings typically begins the building construction
process. It’s difficult to overstate the importance of getting that
beginning done right. All other building work follows the footings,
literally sitting upon them. Take the time to get the footing planning
and execution done well.
One of the first steps in planning the footing work concerns the
location of the surrounding sub grade. In some instances, it’s better to
keep the existing grade low, install the footings with minimal
excavation, then place the fill in the building after footing and
foundation wall excavation. In most instances, it’s easier to bring the
building pad to final sub-grade prior to starting footing excavation.
This is a decision that should be evaluated on each project.
The layout of the footings and what to do with the footing excavation
excess soil material should be considered together. Some
construction supervisor’s use batter boards at each corner to give the line and
the grade of the building. Others use offset hubs to determine line and
an elevation benchmark for grade. With either method, you need to
consider how much offset is required from the actual wall lines in order
to accomplish the excavation. These items should be thought through in
advance of the actual layout and footing excavation in order to proceed
in the most effective manner.
Also consider water related problems at his stage. What will a hard rain
do to the site in the middle of footing excavation? Will footings needed
pumped? Can they be gravity drained? Will mud be created and how will it
be dealt with? Since this is such an important project stage, it’s
prudent to have some contingency plans ready for a few predictable
scenarios.
The construction supervisor need not be paralyzed by planning, spending all his
time considering worst case scenarios. But the construction supervisor should
have put some thought into a few scenarios that may happen and at least
have an idea of how he will proceed. A bit of extra planning at this
stage just makes sense.
The actual installation of concrete footings varies greatly from job to
job. Sometimes footings need to be formed, many times earth forming
works fine (using the Backhoe bucket to neatly excavate the footing size
in the soil). The need for formwork in footings sometimes depends on the
building pad elevation, as discussed above.
The rebar placement in the concrete footing stage generally will be
required to be inspected by the local building official. It’s important
the proper clearances are available (3” from earth, 1 ½” from forms,
etc.) in order to provide protection for the rebar from future
corrosion. It’s also important to tie the rebar securely, due to all the
jostling and pushing that happens during footing concrete placement. The
rebar needs to be in the specified locations, not only before the
concrete is poured, but after.
The concrete placement of footing again varies greatly depending on the
project circumstances. Sometimes the Ready Mix Concrete truck can run
along the footing trench and chute concrete directly into the footings.
Other times concrete buggies or wheel barrows need to carry the concrete
from the truck to the footing. Of course, some projects use concrete
pumps for transporting the concrete to the foundations.
Before the concrete placement starts, the construction supervisor should discuss
some contingencies with the concrete foreman. For example, what happens
if the there is a plant shut down and the concrete trucks stop coming?
What route through the site may the concrete trucks use? Will this
change in foul weather? Where does any extra concrete from a truck get
placed? Where may Ready Mix concrete trucks wash out their mixers and
chutes?
The construction supervisor should be especially vigilant about the concrete
footings. The method of layout should be approved and verified. The
concrete foreman should describe how he will get the top of footings at
the correct elevation. When earth forming is used, there are too many
cases when concrete footing elevations are too high or too low.
There are several ways to make sure the footings are installed correctly
(temporary rebar grade stakes that get pounded down into the wet
concrete after grade is set, wet benching with a laser level and
establishing acceptable grade benches, or several other options). The
construction supervisor doesn’t need to specify the method used, but does need to
understand it and agree that the proposed method will achieve acceptable
results. It’s also valuable to wander by during the first few concrete
footing placements and verify that the proposed method is actually being
appropriately followed.